Case study

Dow Silicones: Precision Lifting for Critical Equipment Removal

Delivering engineered rigging and lifting services to support time-sensitive refurbishment at Dow Silicones

July 28, 2020

article page header image

EnerMech supported Dow Silicones with the safe removal of a CTM mixer and associated components for offsite refurbishment. The project required precise lift planning and execution within a tight outage window, all while maintaining safety and avoiding disruption to ongoing operations.

Our team provided full engineering support, specialist lifting equipment, and experienced rigging personnel. Working collaboratively with Dow’s in-house team, we ensured seamless execution from planning to final survey. The project was delivered on time, on budget, and without incident – earning EnerMech the reinstall scope post-refurbishment.

Key Highlights

  • Engineering support for lift planning, risk assessments, and method statements

  • Supply of specialist lifting equipment and rigging personnel

  • Safe removal and transport loading of CTM mixer and components

  • On-time, on-budget delivery with no safety incidents

  • Reinstall scope awarded following successful execution